ERP writeback
The decision was who owns the money. The queue is just the consequence.
The decision
The fork everyone expects here is synchronous writes versus a queue versus import-only. That was not the real fork. The real decision was who owns the money, and it got settled early: the accounting system contractors already run is the source of truth for actuals. Datum creates the records, exports them, and reads the real numbers back. Datum owns creation, estimates, and projections. The ERP owns job-to-date, billed, invoiced, and committed. Datum never computes actuals by summing its own rows, because two systems that each believe they hold the ledger will eventually disagree, and a construction company settles that argument in favor of accounting every time.
The business problem underneath was stated by my co-founder in one line: quantities were being entered two and three times across systems. So the pipeline runs one direction: a foreman’s timecard quantities carry through to month-close, a PM verifies them, and the verified intent is queued for the ERP.
Why a queue
Because the destination did not exist yet. Integration credentials for the customer’s ERP were months away, and a synchronous write would have had two options while waiting: fail the PM’s month-close, or silently drop the export. Both are wrong. The durable queue holds every verified intent, visibly labeled as awaiting the ERP connection, never silently dropped. When credentials land, the wiring is mechanical.
The queue is boring on purpose: SQL-backed, retry with exponential backoff at one, five, fifteen, sixty, then two hundred forty minutes, five attempts before a row parks as failed with its error message and an admin retry button. Enqueue is idempotent on tenant, resource type, and resource id, keyed for quantities as project by month by cost code, so a double-click cannot double- queue an intent. Re-opening a verified month recalls its queued intents, with one carve-out written into the code: a write that already reached the adapter is a fact, not an intent, and facts do not get recalled. Every boundary crossing lands in an append-only sync log. The retry policy is extracted as a pure function under unit test, because a wrong exhaustion decision either spams an accounting system or silently gives up on posting real money.
The non-negotiable rule for the day writes go live is the double-post story: an ambiguous failure, a timeout after the vendor committed, must not post twice. Every write carries Datum’s resource id as the vendor-side reference, and where the vendor cannot store one, the adapter does a check-before-create read on any retry. No write ships without that story written down.
Normalization is per-tenant configuration, not code: each tenant declares its phase-code segment layout and its cost-type map, eight single-letter codes for the anchor tenant, and an unmapped code passes through labeled rather than breaking the response.
What broke
The worst incident came from the safety apparatus, not the risky part. To build against an ERP with no credentials, a mock adapter serves hand-written fixtures: one invented job with invented contract, cost, and billing figures. Nothing distinguished “developer wants fixtures” from “no ERP is connected,” so every deployed project page dressed those fixtures up as that job’s financials. One hundred seventy-one live jobs showed the same fake $850K. The fix drew the line the design had skipped: fixtures render only where fixtures are asked for, and a disconnected ERP now says so instead of inventing a number.
The fix caused its own smaller lesson. Disconnected endpoints first returned 503, which was the right answer in the wrong tone: healthy screens full of red “Service Unavailable” in the console, and a platform error-rate chart carrying constant noise from a feature that simply was not switched on, which is exactly how a real failure gets lost. They now return a calm 200 with a not-connected code.
Where it stands
Honestly: the seam is built and the connection is not. The queue holds over a hundred verified month-close intents accumulated in production, deliberately, while write-enablement stays off and the real adapter waits on vendor credentials. Reads run end to end against the mock. Reconciliation is designed but not built, and its central rule is already fixed: Datum legitimately runs ahead of the ERP, and where the two disagree on a posted value, the ERP wins and Datum’s row is flagged for a human, never silently overwritten. Would the queue win again? Yes, and earlier. It let the product ship real capture and verification months before the integration it feeds, and the backlog it accumulated is not debt. It is the export, waiting.